The design soot blowing system should
furnish well experienced and approved steam jet type sootblowers for the
superheater, generating bank, economizer and air heater. The design soot
blowing system should arrange the sufficient number of sootblowers for the above
mentioned equipment.
If additional soot blowing
equipment is necessary to maintain the proper surface conditions of
superheater, generating bank, economizer, or air heater, additional equipment
with all piping and wiring should be furnished without any addition to the
contract price during the guaranteed period.
A complete soot blowing system
consisting of all controls, actuators, piping, valves, control panels,
including all necessary starters, switches, relays, protection devices, etc., should
be provided. Steam from high pressure auxiliary steam header should be used as the
cleaning medium. An air operated isolating valve controlled from the remote
control panel should be provided to allow isolation of the soot blowing steam.
Complete remote control system
for each sootblower, including all switches, relays, signal lamps, sequences,
etc., should be provided and installed in the central control room to supervise
operation of blowers.
The system should be able to
allow local manual operation of each sootblower in case of test or failure of
remote control system. The remote control panel should be of the mimic type
suitable for flush mounting. The panel should be complete and fully wired and
tubed with clearly identified terminal blocks and strips.
The panel should be mounted on
the auxiliary control panel in the central control room. All motor starters for
the boiler sootblowers should be furnished. Motor starters should be of magnetic type
mounted on each sootblower with thermal trip relays and start-stop push buttons
for local operation.
Retractable sootblowers should be
provided with a hand crank or drive nut for withdrawing the lance tube in case
of power failure. Sootblowers should be installed in such a manner as to permit
boiler expansion without binding or unbalanced loading. A complete system of
sealing air piping should be furnished to seal the wall sleeves if necessary.
A complete system of aspirating
air piping to permit removal of blower of should be furnished if necessary.
Sealing air and aspirating air piping should have flexible hoses to permit
boiler expansion without binding.
Any drain attack due to soot
blowing on superheater, generating bank, economizer and air heater element should
be absolutely prevented. Special consideration should be given to the method of
efficient draining and heat insulation. Any other cleaning system on heating
surfaces of flue gas side should be given a special consideration and should be
approved by the engineer.
1 comment:
nice post
l like ur artikel
Post a Comment